Construction of the first integrated gas chemical complex. Second phase (Construction of gas separation complex)

Main Project objective: Ethane recovery from Tengiz field Dry gas to supply feedstock to the Polyethylene Project.

Project participants: KMG PetroChem LLP (100% subsidiary organization of NC KMG JSC).

Location: Atyrau region, TCO territory.

Construction period: 2025-2029.

Dry gas processing capacity: 9.1 billion St. m3/year.

Production capacity: up to 1.6 million tons/year (standard) of Ethane; up to 360 kta of Propane.

Process Licensor: US-based UOP for Ethane recovery and Propane Treatment units.

Jobs to be created: ~1,600 during Construction and ~400 during Operation.

Plans for 2024:

  • Re-FEED completion;
  • finalization of the updates to the Design and Estimate Documents;
  • taking FID for the Project to move to the Implementation stage;

Construction of the complex is scheduled to commence in 2025.